ENLARGEMENT OF AN EXISTING COMPOSTING PLANT

Plant Data

General

  • Location:  Manica Lunga district – JOPPOLO GIANCAXIO (AG)
  • Coord. UTM (Fuso 33S):
    374.37 E – 4.135.751 N
  • Site area: 72.000 m2
  • Existing plant surface: 2.100 m2
  • New Plant surface: 17.138,31 m2
  • Enlargement designing period: March 2017
  • Task assigned and carried out: Preliminary and Final design
  • Cost: 11.528.753, 90 €
  • Typology: composting process in bio-tunnel and final maturation by air-forced and dynamic/static windrows.

Treatment

  • Operations according to Encl. B and C referring to Part IV of Law Decree No. 152/06 (D.Lgs. 152/06) and further amendments: D9, R3, R13
  • No. 1 building for composting tunnel: dimensions 38 x 90 m
  • No. 12 composting tunnels (ACT phase):  6 x 32 m each
  • No. 9 air-forced and dynamic windrows: dimensions  5 x 2,7 x 49 m each
  • No. 3 static windrows: 1,600 m3 each
  • New treatment capacity: 56.000 t/year
  • Average process period: 90 days

Plant Description

The proposed plant layout has the main objective to develop a new and larger configuration of an existing composting plant for organic waste treatment and high-quality compost production. The project also provides the technology improvement for the process.

The enlargement of the existing plant consists in the construction of a new building in which the composting process will start inside no. 12 closed tunnels (process period 4 weeks).

After the intense composting phase, the material will be moved to the final maturation section (after screening operation). This phase will occur in dynamic windrows subjected to forced ventilation inside a closed concrete building. A further final maturation phase is also provided through static windrows, so that the composting process can be completed, obtaining a high-quality compost for sales.

The project provides an increasing of the composting treatment capacity equal to 30.000 t/year, which increases, together with the existing authorized capacity 26.000 t/year (AIA authorization released by D.D.S. n. 1897 del 12/11/2014 for R3, R13 operation), the plant capacity up to 56.000 t/year.